You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation: I. Availability of re-usable test systems and documentation from previous, similar projects II. Unexpected timing of components arrival III. Stability of the integration test team (no turnover) IV. Many and geographically distributed sub-teams Which of the following statements is true?
Select one answer.