ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Activity duration estimates provide insights into the time allowances for activities or the project as a whole. A wider range in the estimates often indicates a higher degree of risk and uncertainty. This input is valuable in identifying potential risks related to schedule constraints or unforeseen delays.