You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?
Select one answer.
Marked answer: C
Community Discussion
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Chose C1
The purpose of repeated risk identification meetings is to identify "new" risks
Chose C1
to identify the emerging risks
Chose C1
Please remove my answer, I meant this to be on #3 (CPS13, thank you).