ISACA Certified in Risk and Information Systems Control · Isaca
Select 3 answers.
This question asks for 3 answers, but our data marks only 1. Compare with the community discussion below for the full answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Monitoring risk is before its occurrence.
The three correct tasks to perform in reaction to a risk event occurrence are: A. Monitor risk: Continuously evaluate the risk to understand its impact and ensure proper mitigation measures are taken. B. Maintain and initiate incident response plans: Execute predefined response plans to address the risk effectively and minimize its consequences C. Update risk register: Document the details of the risk event, including its impact, response actions, and any updates to mitigation strategies. Option D, communicating lessons learned, is typically done after the risk is resolved to improve future planning rather than as an immediate reaction