Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D. Project Issue A project issue is an event or condition that has already happened and is negatively affecting the project's objectives. In this case, the delay in issuing the permit is an existing problem that is impacting the project's timeline.
Not sure I understand or agree with this explanation. When a risk happened we take risk response actions e.g. mitigate, accept etc, and the scenario in this question fits the risk criteria, so why it can’t be classified as Project Risk?
In my opinion, the delay to the start (of this stage) of the project is an Issue because it has already occurred. However, the delay issue also poses follow-on risks of delays to future stages and completion of the project, and cost overruns.