ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
C. Exploiting. Exploiting is a risk response strategy where the project manager takes advantage of an opportunity to maximize the positive impact on the project's objectives. In this case, Shawn identified an opportunity to complete the project more cost-effectively by implementing new software and training, which would save the project nearly $65,000. By agreeing to the software and changing the project management plan accordingly, he is exploiting this opportunity to enhance the project's outcomes.
I think the main difference is "assurance", In Enhance, there is no assurance that the event will occur while in Exploit there is assurance that the event will happen as the risk manager will do everything to make sure it happen.
This is from ProjectCubicle.com... Enhance and Exploit are two positive risk response strategies. The main difference between them is; in the enhance strategy you are trying to increase the probability of the opportunity happening but in the exploit strategy you increase the probability of the opportunity to 100%.