ISACA Certified in Risk and Information Systems Control · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Correct answer B and not D. At every status meeting the project team project risk management is an agenda item. While it is important to discuss project risks at status meetings and have risk management as a regular agenda item, the best practice for comprehensive risk management typically involves more formal and structured reassessment at key project milestones rather than just during routine status meetings. Milestone reviews allow for a more in-depth analysis and evaluation of risks at critical points in the project timeline.