Cognitive Project Management in AI · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The six iterative CPMAI phases are: Phase I Business Understanding, Phase II Data Understanding, Phase III Data Preparation, Phase IV Model Development, Phase V Model Evaluation, and Phase VI Model Operationalization. The first three are data-centric and feed the modeling phases, mirroring and extending the CRISP-DM lifecycle. The other answer options describe generic software or design lifecycles, not CPMAI.