Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
ISACA Certified in the Governance of Enterprise IT · Isaca
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Portfolio management allows you to analysis and manage each project appropriately
I think A should be the correct answer. Portfolio management allows for an eagle view of all projects and will be the best tool to alleviate what is on the scenario. A business case is focusing on one project at a time and will not provide a view of how that single project impacts on other projects
I agree with D. To prioritize funding, you need numbers like NPV or ROE. That makes a priority list which is used by the portfolio management to handle the resource shortage.