Question 18 of 155
Free Preview · 155 of 514 · questions 1–155 of 514 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The Work Breakdown Structure (WBS) is a key tool for defining the scope of work and developing estimates for a project. It breaks down the project into smaller, manageable components, making it easier to estimate time, cost, and resources required for each task. The BABOK Guide (Chapter 5: Requirements Life Cycle Management - Prioritize Requirements) and project management best practices emphasize the use of a WBS to organize and define the total scope of the project. The WBS helps ensure that all work is accounted for and provides a clear structure for estimating and planning.
B. Work Breakdown Structure
BABOK Section 3.1.5: Plan Business Analysis Approach, a Work Breakdown Structure (WBS) is an important tool for defining the scope of work and developing estimates for a project or initiative. A WBS breaks down the entire scope of work into smaller, manageable components or tasks, which makes it easier to assign responsibilities, estimate costs, and track progress. It provides a hierarchical view of all the tasks required to complete the endeavor, helping the business analyst (BA) define and organize the scope effectively.