Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The project management plan includes subsidiary plans for each knowledge area: scope, schedule, cost, quality, resource, communications, risk, procurement, and stakeholder management plans. A "team performance evaluation plan" is not a standard subsidiary plan in the PMBOK framework. While team performance is addressed within the Resource Management Plan, it does not have its own standalone subsidiary plan. Understanding the components of the project management plan is essential for the CAPM exam.