Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A Directive PMO has the highest degree of control because it directly manages projects. Project managers are assigned by and report to the directive PMO, which takes control of project execution. A Controlling PMO provides support and requires compliance with frameworks or methodologies through adoption of templates, forms, and tools. A Supportive PMO provides a consultative role, supplying templates, best practices, and training with a low degree of control. "Advisory PMO" is not a standard PMI classification.