Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The project charter is typically signed and issued by the project sponsor or an executive at a level appropriate to fund the project. This individual has the organizational authority to commit resources and formally authorize the project. The project manager does not sign the charter - they receive their authority from it. The team lead and customer may provide input but do not have the organizational authority to formally authorize a project. This is an important governance concept: the PM authority comes from the charter, which comes from the sponsor.