Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The project charter is a document issued by the project sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It includes the project purpose, high-level requirements, summary budget, summary milestones, success criteria, and the assigned PM. It is not a detailed schedule (that is the project management plan), not a risk register, and not a contract (contracts are procurement documents).