Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Project constraints are interdependent. When new requirements are added (scope increase) and the deadline is fixed, the project manager must adjust other constraints to accommodate the change. The cost may increase to add more resources, the schedule may need to be compressed, scope may need to be reduced elsewhere, or quality may be impacted. This illustrates the fundamental concept that changing one constraint inevitably impacts others, which is why integrated change control is essential.