Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A milestone is a significant point or event in the project that has zero duration. Milestones represent key achievements, decision points, or deliverable completions - such as "Design Approved" or "Phase 2 Complete." They do not consume resources or time; they simply mark that something has been accomplished. The longest-duration task is part of the critical path concept, the first activity in each phase is simply a starting activity, and critical path tasks are activities with float constraints, not milestones.