- When a change request is submitted, the project manager should first assess the impact of the change on all project constraints including scope, schedule, cost, quality, resources, and risk. This impact assessment provides the information needed for the CCB (or appropriate authority) to make an informed decision about whether to approve, defer, or reject the change. Implementing without assessment or rejecting without analysis are both inappropriate responses.