Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A communications management plan includes stakeholder communication requirements, information to be distributed, frequency and format, responsible persons, escalation procedures, methods of communication, and glossary of terms. Detailed project cost estimates belong in the cost management plan and cost baseline, not the communications management plan. The communications plan focuses on how information flows, not the content of cost estimates.