Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Work Performance Information (WPI) is the analyzed version of raw work performance data, providing insight into project progress and status. It is typically an output of monitoring and controlling processes.
In this process, Work Performance Information refers to the data collected about project execution and performance, which is used to assess how effectively the project team is engaging stakeholders. This information aids in evaluating the current status of stakeholder engagement and helps in making informed decisions about managing stakeholder relationships throughout the project lifecycle.
C. Please see 5.9 Monitor Communications - Outputs - Work Performance information is an output of the stakeholder management plan figure 5-10