Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A resource histogram is a bar chart that shows the number of resource hours (or units) required per time period. It helps project managers visualize resource allocation, identify periods of overallocation, and plan for resource leveling. A horizontal line on the histogram may indicate the maximum available hours, making it easy to spot when demand exceeds capacity.