Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- In a functional organization, the functional manager has full authority over resources, budgets, and project decisions. The project manager role may not even formally exist, or if it does, the PM has very little authority. In a weak matrix, the PM has limited authority. In a strong matrix, the PM has significant authority. In a projectized organization, the PM has full authority over resources and the project.