Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Mitigate is a risk response strategy that seeks to reduce the probability or impact of a threat to an acceptable level. By selecting a backup vendor, the team is reducing the impact of the risk (delivery delay) without eliminating it entirely. Avoid would eliminate the risk completely, transfer would shift the impact to a third party (like insurance), and accept would take no proactive action.