Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The PERT weighted average formula is: Expected Cost = (Optimistic + 4 x Most Likely + Pessimistic) / 6. Expected Cost = ($40,000 + 4 x $50,000 + $90,000) / 6 = ($40,000 + $200,000 + $90,000) / 6 = $330,000 / 6 = $55,000. The PERT formula gives four times the weight to the most likely estimate, reflecting that it is the most probable outcome.