Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- When current cost performance is expected to continue for the remainder of the project, EAC = BAC / CPI = $200,000 / 0.80 = $250,000. This formula assumes the same cost efficiency will persist. A CPI of 0.80 means for every dollar spent, only $0.80 worth of work is completed, so the project will ultimately cost $250,000 instead of the original $200,000 budget.