- Parametric estimating uses a statistical relationship between historical data and other variables (such as square footage, lines of code, or hours per unit) to calculate estimates. The example of $150 per square foot multiplied by total square footage is a classic parametric estimate. This technique can produce higher levels of accuracy depending on the quality of the underlying data and the model used.