Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Total float is calculated as Late Start minus Early Start (LS - ES) or Late Finish minus Early Finish (LF - EF). In this case: LS - ES = 13 - 10 = 3 days, or LF - EF = 18 - 15 = 3 days. This means the activity can be delayed by 3 days without impacting the project end date. An activity on the critical path would have zero total float.