Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Finish-to-Start (FS) is the most commonly used dependency type in project scheduling. It means the successor activity cannot start until the predecessor activity finishes. For example, you cannot begin painting a wall (successor) until the drywall installation (predecessor) is complete. FS relationships represent the natural logical sequence of work.