Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Total float is calculated as the difference between the critical path duration and the path duration. The critical path is Path B at 22 days (the longest path). Path C has a duration of 20 days. Total float = 22 - 20 = 2 days. This means activities on Path C can be delayed by up to 2 days without delaying the project completion date.