Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The critical path is the longest sequence of activities through the project network diagram that determines the minimum project duration. Activities on the critical path have zero or negative total float, meaning any delay to a critical path activity will delay the entire project. Identifying the critical path is essential for effective schedule management.