Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Decomposition is the technique of subdividing project deliverables and project work into smaller, more manageable components. It is the primary technique used to create the WBS. The process continues until the deliverables are broken down to the work package level, where cost and duration can be reliably estimated. Rolling wave planning is an iterative planning technique, not a decomposition method.