Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Validate Scope focuses on gaining formal acceptance of deliverables from the customer or sponsor, emphasizing whether the deliverables meet the agreed-upon scope. Control Quality focuses on verifying that deliverables meet the specified quality requirements and are correct. Control Quality is typically performed before Validate Scope, as deliverables should meet quality standards before being presented for acceptance.