Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The WBS dictionary provides detailed information about each WBS element including a description of work, acceptance criteria, responsible organization, schedule milestones, associated activities, cost estimates, and quality requirements. Detailed daily task assignments are operational-level details managed through resource calendars and project schedules, not the WBS dictionary.