Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The primary output of the Validate Scope process is accepted deliverables. This process involves the formal acceptance of completed deliverables by the customer or sponsor. The customer inspects each deliverable and either accepts or requests changes. Accepted deliverables are then documented and forwarded to the Close Project or Phase process.