Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The project manager's review of change requests for project documents, deliverables, and the project plan falls under the Perform Integrated Change Control process. This process ensures that all changes are managed systematically, considering their impact on the project's scope, schedule, cost, and other aspects.
That the process
D. Perform Integrated Change Control