Question 24 of 37
Free Preview · 37 of 123 · questions 1–37 of 123 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Monte Carlo and probabilistic forecasting use empirical throughput — the actual count of items completed per unit of time across a meaningful historical sample. Throughput is more reliable than story-point velocity because it sidesteps estimation noise. Scrum.org's Kanban guidance and PSPO II both favor throughput-based forecasting.