At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint. Which of the following two actions would you support? (Choose two.)
Select 2 answers.
Marked answer: A
This question asks for 2 answers, but our data marks only 1. Compare with the community discussion below for the full answer.
Community Discussion
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Chose AD1
A D are correct
1
Yes, A and D.
1
A and D are correct