Question 37 of 46
Free Preview · 46 of 153 · questions 1–46 of 153 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The PMO should establish a transparent prioritization framework that evaluates projects based on strategic value, risk profile, resource requirements, interdependencies, and time sensitivity. This framework enables consistent, objective decision-making and reduces conflict. Ad hoc approaches like first-come-first-served or escalating everything to the CEO are unsustainable and create bottlenecks.