Question 30 of 46
Free Preview · 46 of 153 · questions 1–46 of 153 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Correct answer : B — Deliver continuous training, coaching, and dissemination of best practices. A . Incorrect. While cost reduction and operational efficiency are important, they are tactical rather than strategic objectives. A PMO's strategic focus should align with broader organizational goals, such as improving capability and value delivery, not just operational metrics. B . Correct. A PMO strategy emphasizes enabling the organization through continuous training, coaching, and sharing best practices. This builds project management maturity, improves delivery consistency, and supports long-term strategic alignment with enterprise goals. C . Incorrect. Consolidating all project resources under direct PMO control is a structural decision rather than a strategic focus. PMOs typically coordinate and govern resources without necessarily owning them, and this approach may create silos rather than fostering cross-functional collaboration. D . Incorrect. Generating monthly status reports and metrics is a tactical monitoring activity, not a strategic objective. While reporting supports oversight, it does not by itself define the PMO's strategic role in developing organizational capability and performance.