Question 19 of 46
Free Preview · 46 of 153 · questions 1–46 of 153 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A Directive PMO has the highest level of control, directly managing projects by assigning project managers and taking ownership of project delivery. A Controlling PMO provides frameworks and requires compliance but doesn't directly manage. A Supportive PMO offers templates, best practices, and training with minimal control. Understanding these types is essential for PMO strategy.