Question 5 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The critical path is the longest sequence of logically dependent activities through the project network diagram, determining the minimum possible project duration. Activities on the critical path have zero total float — any delay to these activities directly delays the project completion date. The critical path may shift during project execution as activities are completed ahead of or behind schedule.