Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
Question 47 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The To-Complete Schedule Performance Index (TSPI) calculates the schedule efficiency required on all remaining work to meet a target completion date. It is the schedule equivalent of the cost TCPI. If TSPI is significantly greater than 1.0, achieving the target date requires unrealistically higher productivity on remaining work, signaling that the target date is likely unachievable without schedule compression or scope reduction.