- Critical Chain Project Management (CCPM), based on Goldratt's Theory of Constraints, identifies the critical chain as the longest sequence of dependent activities considering both logical and resource dependencies. CCPM removes hidden safety margins from individual activity estimates, aggregates them into project-level and feeding buffers, and manages buffer consumption as the primary schedule health indicator. This approach often produces shorter, more reliable schedules.