Question 33 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule Variance (SV) is calculated as EV - PV (Earned Value minus Planned Value). A negative SV indicates the project is behind schedule because the value of completed work (EV) is less than the value of planned work (PV). For example, SV = -$10,000 means $10,000 worth of planned work has not yet been completed. SV = 0 means on schedule, and positive SV means ahead of schedule.