Question 3 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The four types of logical relationships in project scheduling are Finish-to-Start (FS — successor starts after predecessor finishes), Start-to-Start (SS — both start together), Finish-to-Finish (FF — both finish together), and Start-to-Finish (SF — predecessor start enables successor finish). FS is the most common relationship. Understanding all four and when to use each is fundamental to building accurate schedule logic.