Question 28 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Monte Carlo simulation in schedule risk analysis involves assigning three-point estimates (optimistic, most likely, pessimistic) or probability distributions to activity durations and running thousands of simulations with random sampling. The result is a probability distribution of project completion dates and milestone dates, showing confidence levels (e.g., 'P80 completion date = June 15'). This is far more informative than a single deterministic date.