Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
Question 26 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The backward pass is the second step in CPM calculations, moving backward through the network from the project end date to determine the latest allowable start (LS) and latest allowable finish (LF) for each activity without delaying the project. LF is determined by the earliest LS of all successors, and LS = LF - Duration. The difference between early and late dates (LS - ES or LF - EF) yields total float.