Question 44 of 100
Free Preview · 100 of 333 · questions 1–100 of 333 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Risk management plan consists of risk statement, RBS, defination of threats and opportunities, P &I matrix, And Risk Register contains list of identified risk, qualitative and quantitative analysis, risk response planning, risk owner names. AND Project charter is only used for planning in begining, so the correct answer is communication plan. hope it clears.
Careful on this type of question. It is reaching back to PMP materials here.