Question 4 of 100
Free Preview · 100 of 333 · questions 1–100 of 333 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The risk management plan (which establishes the framework) should first define the methodology (how risk management will be performed), roles and responsibilities (who will do what), and timing (when risk activities will occur). These foundational elements guide all subsequent risk activities. You cannot create detailed response strategies or a complete risk list until the framework is established, and thresholds require understanding the methodology first.