Risk owners should be identified as early as possible in the project lifecycle. Ideally, this should happen during the risk identification phase, which is part of the project planning process.
In Identify Risks, you should look for potential risk owners. However, in Plan Risk Responses, you ALLOCATE risk owners to every risk you have.
The question does not say "Possible risk owner" which only happens in Identofy risks therefore the answer is A