Question 33 of 100
Free Preview · 100 of 333 · questions 1–100 of 333 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
By discussing the project schedule with the executive sponsor, the project manager can share the findings from the risk analysis and highlight the schedule's shortcomings. Together with the executive sponsor, they can determine a strategy for updating the risk management plan and risk response plans to address the schedule issues and mitigate potential risks.